Nov. 16, 2022
FIDIC Red Book 1999 – The Force Majeure Clause
The definition of force majeure provided in the FIDIC Red Book 1999 Edition form in Clause 19 is widely drawn. Sub-Clause 19.1 defines a force majeure event as one:
A) which is beyond a Party’s control,
B) which such Party could not reasonably have provided against before entering into the Contract,
C) which, having arisen, such Party could not reasonably have avoided or overcome, and
D) which is not substantially attributable to the other Party.
Force Majeure may include but is not limited to, exceptional events or circumstances of the kind listed below, so long as conditions (A) to (D) above are satisfied:
1) Munitions of war, explosive materials, ionizing radiation, or contamination by radioactivity, except as may be attributable
to the Contractor’s use of such munitions, explosives, radiation or radioactivity, and
2) Natural catastrophes such as earthquakes, hurricanes, typhoons, or volcanic activity.
3) War, hostilities (whether war be declared or not), invasion, the act of foreign enemies,
4) Rebellion, terrorism, revolution, insurrection, military or usurped power, or civil war,
5) Riot, commotion, disorder, strike or lockout by persons other than the Contractor’s Personnel and other employees of the
Contractor and Sub-Contractors.
There is a broad definition of force majeure and it should be remembered that the examples listed above are not an exhaustive list but, reflect the basic premise of a force majeure clause, namely that it serves to exempt a party from performance on the occurrence of a force majeure event.
A problem that has been identified with the FIDIC Red Book 1999 Edition is that there is a risk of potential overlap and/or contradiction between Sub-Clause 19.1 and the court's definition of force majeure under the Ethiopian Civil Code. Indeed, incorporating a clause such as Clause 19 into a contract not only duplicates what is usually provided for under law but also enlarges the scope of the meaning and application of force majeure. This could result in the Parties getting into a contradictory situation.
There was no specific force majeure clause in the Red Book FIDIC 4th Edition. However, the Contractor was afforded some protection by Clause 65, which dealt with special risks including the outbreak of war, and Clause 66, which dealt with payment when the Contractor was released from the performance of its contractual obligations. The scheme of the FIDIC form is that the party affected, which is usually the Contractor but could also be the Employer, is entitled to such an extension of time as is due and (with exceptions) additional cost where a “force majeure” occurs.
For Clause 19 to apply, the force majeure event must prevent a Party from performing any of its obligations under the Contract. The now classic example of this is the refusal of the courts to grant relief as a consequence of the Suez crisis during the 1950s. Those who had entered into contracts to ship goods were not prevented from carrying out their contractual obligations as they could go via an alternative route even though the closure of the Suez Canal made the performance of that contract far more onerous it did not make it impossible.
Sub-Clause 19.7 of the FIDIC Red Book 1999 Edition is also of interest. Here, the parties will be released from performance (and the Contractor is entitled to specific payment) if (i) any irresistible event (not limited to force majeure) makes it impossible or unlawful for the parties to fulfill their contractual obligations, or (ii) the governing law so provides. It acts as a fallback provision for extreme events (i.e., events that render the contractual performance of the contract illegal or impossible) which do not fit within the strict definition of force majeure laid out under Sub-Clause 19.1. It also grants the party seeking dismissal the right to rely on any alternative relief which may be contained in the law governing the contract.
If common law applies, the affected party will be able to rely on the common law concept of frustration, which occurs whenever the law recognizes that without the default of either party a contractual obligation has become incapable of being performed because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract. To claim frustration, it is not enough for a Contractor to establish that new circumstances have rendered its contractual performance more onerous or even dangerously uneconomic. For frustration to be held by the courts as grounds for termination, it is a requirement that a radical turn of events completely changes the nature of the contractual obligations. It is a difficult test to fulfill, but not as difficult as that of Sub-Clause 19.4 (force majeure) or the first limb of Sub-Clause 19.7 which both refer to the concept of impossibility (or illegality).